Dredging Up the Past: Switzerland's 20-Million-Franc River Scrub
A decade after a toxic chemical spill, heavy machinery is tearing up the pristine Swiss National Park to save it.

The Swiss National Park in Graubünden is supposed to be a sanctuary of untouched nature. Instead, it currently resembles an industrial mining operation. Heavy excavators are churning through the Spöl riverbed, shattering the alpine silence to rectify a decade-old chemical blunder.
Ten years ago, routine maintenance on the Punt dal Gall dam near Lake Livigno went predictably wrong. Workers sandblasting an old anti-rust coating released polychlorinated biphenyls into the water. Now, the wealthy Alpine nation is dipping into its deep pockets, spending 20 million Swiss Francs to dredge the consequences out of the mud.
Polychlorinated biphenyls, better known as PCB, are highly toxic and carcinogenic. Though banned in 1986, the substance stubbornly persists in the environment, historically favored in paints, sealants, and fluorescent lamps. In the Spöl river, the chemical settled into the sediment, contaminating a five-kilometer stretch of what is supposedly pristine wilderness.
The local wildlife has absorbed the cost. National Park Director Ruedi Haller confirmed that the contamination persists, noting that while overall levels have decreased, dissolved PCB remains in the water. The eggs of local dippers are tainted, and the fish carry toxicity levels that make them entirely unfit for human consumption.
The Swiss state system, ever methodical and well-funded, spent years navigating negotiations and partial cleanups before launching this massive intervention. Before the heavy machinery could roll in this past April, the river had to be emptied of its inhabitants. Last September, exactly 12,000 brown trout were fished out and relocated, clearing the way for the total excavation of a three-kilometer river zone.
The logistics of this operation are staggering. Crews are removing 37,000 tons of stone, gravel, and sand. Of this, 10,000 tons of fine sediment are so hopelessly laced with PCB that they cannot be washed or treated. This toxic fraction, enough to fill roughly 2,500 trucks, is being hauled away for specialized disposal.
Operating a toxic waste site inside a strict nature reserve presents a unique set of physical and bureaucratic hurdles. Construction manager Melanie Eberhard highlighted the tight, sensitive terrain and the extreme environmental regulations imposed on the project, a first for the national park.
The human element requires equally stringent management. Because PCB can be absorbed through the skin, laborers are forced to wear long sleeves despite the physical exertion. Eating, drinking, and smoking are strictly prohibited on the site to prevent accidental ingestion of the chemical, adding a layer of strict discipline to the daily grind.
The immediate result of this environmental rescue mission is, ironically, total ecological disruption. The fish are gone, and the micro-habitats of aquatic insects have been scooped into dump trucks. Land animals like chamois and bearded vultures have simply grown accustomed to the mechanical noise, observing the wealthy nation's attempt to engineer its way out of a mess.
Haller expects it will take several years for the ecosystem to recover its former rhythm. The ultimate ambition is a clean Spöl river, flowing as if the industrial mishap never occurred. Nature, carefully managed and heavily funded by a state that can easily afford it, will eventually be allowed to resume its course.
Written by Freya Stensrud freya.stensrud@alpineweekly.com